PROJECTS IN PROGRESS
VILLA MARCO
STAGES 
  
  
  The construction stages 
  Excavations for the foundation 1-3 weeks 
  Laying of The Foundations 15-30 days 
  Concrete for Each Floor 7-10 days 
  Walls and Isolation 15-30 days
Roof & roof tiles 15-30 days
  Installation of water pipes 2-3 weeks 
  Plaster and installation of heating 20-30 days 
  Doors and Windows 1-2 weeks 
  Floors 3-4 weeks 
  Painting 20-30 days 
  Finishing 2-3 weeks